Monday, 12 November 2012

Lukasz grinding off the steel bars that were used to hold the temporary shuttering in place.

Saturday, 10 November 2012

The north-west end of Grove Park in 1905.

An auction plan from 1836.
The auction of what is now Grove Park took place in Garroway's Coffee House.

The view from Frank's pop-up rooftop cafe in downtown Peckham.
Frank's is open for 4 months every summer and hosts a sculpture show and live events.

A green roof by Blackdown Horticultural, who will be planting our roofs.
The roofs will be planted with a mixture of native species, to encourage biodiversity.

Anagram for the day.
A late autumn afternoon in Grove Park.


The boys are pouring concrete to form the basement retaining walls.
The shuttering has to be very strong - concrete weighs 2.4 tonnes per cubic metre and there are 10 cubic metres behind there.

The concrete pump is back.

Tuesday, 6 November 2012



The boys work into the evening to lift the next 3 panels.

The first 3 panels in position.
The slot to the left is for the glass floor panel which will flood the basement with natural light.

Precast concrete panels being craned into position.
These are permanent formwork onto which the concrete ground floor slab is poured.

The garden of 38 Grove Park, reinforcing mesh and site accommodation.

Friday, 2 November 2012

First floor plan.

Ground floor plan.

Basement floor plan.

Thursday, 1 November 2012

A draft computer generated image of Paddock House, one of the two houses we are building.

Benni and Jonni are building up the party wall between the two houses.

The Council is renewing the pavements and road surface all round Grove Park.

The concrete pump at dusk.



Pouring the concrete for the last quarter of the basement slab.

Sunday, 28 October 2012

The shuttering is in place for the last quarter of the basement slab.
Concrete pouring on Monday.

The last pile of clay ready for removal.  The big Dig is over.

Preparing the last quarter of the basement slab.

The shuttering for the rear basement retaining wall.
The weight of the wet concrete is enormous, so raking props are arranged to resist the forces until the concrete sets.

Friday, 19 October 2012

The boys have worked all day in the rain - na zdrowie!

Pouring the concrete for the upstand wall.
The basement slab is next.
The concrete pump for the basement slab.
It has a reach of up to 31 metres.

Tuesday, 16 October 2012




The Big Dig is almost over...

Sunday, 14 October 2012

Anagram for the day.

The reinforcing mesh for the basement walls.

161 contiguous piles form the perimeter of the basements.
These concrete piles are 350mm diameter, at 525mm centres.  They reinforce the ground until the basement walls are cast against them,


The inboard piles before being broken down to basement slab level.
These piles are 17.5 metres long and will take the loads from around the staircase atrium.


Peter and Hattie, our gorgeous structural engineers.

Structural engineers Peter and Hattie inspecting the retaining wall.

Fixing the shuttering.

The first section of basement slab and wall is cast.

Tuesday, 2 October 2012

Erecting the shuttering for the basement retaining walls.

The reinforcing mesh for the basement retaining walls.

Friday, 28 September 2012

Billy Lloyd's photograph of a slip-cast mug mould in a pottery works in Stoke. 
Billy will be making the light fittings for the houses.
The light fittings will be manufactured (slip-cast) then crafted (turned on a wheel), meaning each will be unique.